Proof
Fourteen first-of-a-kinds.
Delivered from the owner's side of the table — first-of-a-kind facilities that had to be engineered, permitted and built with no precedent to copy, the safety record they were delivered with, and every phase each project was carried through. The fourteen are numbered below; the unnumbered lines are further distinctions on the same projects.
Executive career profile PDF, one page
Delivery record
Eight major projects, concept to operations.
That career was deliberate. I went looking for both sides of everything: small companies with no playbook and large ones with heavy governance; offshore and onshore; greenfield and brownfield; half a billion to ten billion; every project phase, most project departments, and a run of world and country firsts.
Each side does something better than the other and something worse. The disciplines I run are largely the same on every project. The judgment lies in how you apply them with these people, in this country, under this contract.
$20B+executed
8major projects
25years, client-side
14first-of-a-kind facilities
20 MTPADelivered LNG capacity, export and import
200 MWDelivered gas-fired power generation
151modules and jackets, ~100,000 tonnes fabricated and installed
24Mwork hours LTI-free, directly accountable
Direct delivery accountability
Project detail — open any project to see the configuration, technology, contractor and contracting strategy.
Project
Pre-FEED · FEL 2
FEED · FEL 3
FID Readiness
EPC Execution
Operations
St Charles Clean Fuels
Blue ammonia and hydrogen · 1.4 MTPA · ~$4B · Louisiana, USA
Senior Project Director · 2024–2026Sole accountability · FEED & FID readiness
- Joint venture
- Copenhagen Infrastructure Partners (operator and project lead) and International-Matex Tank Terminals
- Configuration
- Greenfield and brownfield onshore blue ammonia/hydrogen facility; first phase one train at 1.4 MTPA
- Technology
- Topsoe
- Power
- 100 MW grid import
- Modularization
- 78 modules – total weight of 33,000 tonnes
- FEED contractors
- Hyundai, and S&B Engineers and Contractors
- Contracting
- EPC&C lump sum, provisional sum and reimbursable — approx. $4B
Woodfibre LNG
LNG export · 2.1 MTPA · ~$6B · Squamish, British Columbia, Canada
Senior Project Director / VP Projects · 2024Sole accountability · EPC execution
- Joint venture
- Pacific Energy (operator and project lead) and Enbridge
- Configuration
- Greenfield onshore LNG liquefaction, one train at 2.1 MTPA, and the conversion of two LNG carriers (cargo volume 125,000 m³ each) into Floating Storage Units (FSUs)
- Technology
- APCI C3MR
- Power
- 140 MW hydroelectric grid import — fully electrically driven
- Modularization
- 16 modules (total weight of 42,000 tonnes) including 2 mega-modules, fabricated at QMW’s yard in Qingdao, China
- Principal contractor
- McDermott International; major subcontractors Kiewit and Ledcor Bird
- Contracting
- EPC&C lump sum and reimbursable — approx. $6B
Energía Costa Azul LNG
LNG export · 3.25 MTPA · ~$2B · Ensenada, Mexico
Project Director · 2020–2023Sole accountability · Pre-FID through EPC execution
- Joint venture
- Sempra Infrastructure (operator and project lead) and TotalEnergies
- Configuration
- Brownfield onshore LNG export facility, one train at 3.25 MTPA, built inside a live operating regasification terminal
- Technology
- APCI DMR, with hybrid seawater and air cooling
- Power
- 60 MW on-site (5 × Solar Titan 130) plus 40 MW grid import
- Mechanical drives
- 2 × GE LM6000, 60 MW each
- Principal contractor
- Technip Energies; major subcontractors ICA Fluor and Bonatti
- FEED contractors
- Bechtel and Technip Energies — competitive FEED
- Contracting
- EPC&C lump sum — approx. $2B
Hong Kong Offshore LNG Terminal
FSRU, offshore platform and subsea pipelines · 7.1 MTPA · ~$1.5B · Hong Kong
Project Director · 2018–2020Sole accountability · FEED through EPCIC
- Joint venture
- CLP (operator and project lead) and Hong Kong Electric
- Configuration
- Double-berth offshore LNG platform — fixed multi-jacket substructure and topsides — with permanently moored FSRU, two subsea pipelines (30″ × 46 km and 20″ × 18 km), and onshore receiving facilities at two power stations totaling 10 GW
- FSRU
- MOL Challenger — 263,000 m³ storage, 1,000 MMSCFD regasification
- Principal contractor
- China Offshore Oil Engineering Corporation (COOEC)
- Fabrication yards
- COOEC-Fluor Heavy Industries, Zhuhai; Chiwan Sembawang, Shenzhen
- FEED contractor
- Worley Parsons (now Worley)
- Modularization
- 20 jackets and 4 topsides modules – total weight of 4,000 tonnes
- Classification Society
- Bureau Veritas
- Contracting
- EPCIC lump sum — approx. $1.5B
Kwispaa FLNG
FLNG · 4 × 6 MTPA · Sarita Bay, Vancouver Island, Canada
Project Manager · 2016–2018
- Developer
- Steelhead LNG
- Configuration
- Four jetty-moored new-build FLNG facilities at 6 MTPA each — two 3 MTPA trains per floater on a QMAX-derived hull — plus onshore gas pre-treatment and power generation
- Technology
- APCI DMR, air cooled, fully electrically driven
- Power
- 1,000 MW on-site CCGT — 16 × Siemens SGT-800 at 53 MW each, plus 8 steam turbines
- Modularization
- 24 modules – total weight of 45,000 tonnes
- Hull & modules fabrication contractor
- Hyundai Heavy Industries
- FEED contractor
- Worley Parsons (now Worley)
- Classification Society
- Det Norske Veritas (DNV)
West Africa FLNG
FLNG · 2.5 MTPA · Fortuna, New Age Congo & Cameroon
FLNG Project Manager · 2014–2016
- Operator
- Bumi Armada
- Configuration
- New-build offshore FLNG — two trains at 1.25 MTPA LNG each, plus 0.4 MTPA LPG and 0.1 MTPA condensate
- Technology
- APCI SMR
- Power
- 75 MW on-board gas-fired generation (3 × GE PGT25)
- Mechanical drives
- 4 × GE PGT25, 26 MW each
- Modularization
- 17 modules – total weight of 45,000 tonnes
- EPC contractors
- SAIPEM S.p.A, and Daewoo Shipbuilding and Marine Engineering, DSME (now Hanwha)
- Classification Society
- Lloyd’s Register
- Bid portfolio
- Fortuna FLNG (2.5 MTPA), Congo FLNG (1 MTPA), Cameroon Near Shore FLNG (1.5 MTPA)
Gladstone LNG
LNG export · 7.8 MTPA · ~$10B · Curtis Island, Australia
Project Manager, reimbursable scope · 2008–2014
- Joint venture
- Santos (operator and project lead), TotalEnergies, PETRONAS and Korea Gas Corporation (KOGAS)
- Configuration
- Greenfield onshore modularized LNG export facility, two trains at 7.8 MTPA
- Technology
- ConocoPhillips Optimized Cascade
- Power
- 70 MW on-site (6 × Solar Titan 130)
- Mechanical drives
- 12 × GE LM2500+G4, 25 MW each
- Modularization
- 111 modules (total weight of 51,000 tonnes) fabricated at AG&P’s yard, Batangas, Philippines
- Principal contractor
- Bechtel Oil, Gas and Chemicals
- Contracting
- EPC&C lump sum approx. $9B, plus provisional sum and reimbursable scope approx. $1B
West Kimberley Power Project
Small-scale LNG & gas power · 200 tpd + 4 regas terminals and power stations · ~$0.5B · Australia
Engineering Manager & Lead Commissioning Engineer · 2005–2008
- Owner
- Energy Developments (EDL)
- Configuration
- A complete small-scale LNG chain — one 200 tonne/day liquefaction train at Karratha, six LNG road tankers, and four remote regasification terminals with gas-fired power stations at Broome, Derby, Fitzroy Crossing and Halls Creek
- Technology
- Salof Refrigeration liquefaction (now Baker Hughes)
- Power
- 70 MW installed — 38 × Caterpillar reciprocating gas engines and 17 diesel engines
- Contracting
- Discipline-based service contracts, with project management, engineering, procurement and commissioning executed directly by the owner — approx. $0.5B
Santos Ltd — Operations Brownfield Projects†
Brownfield oil & gas · Moomba & Ballera, Australia
Senior Project Engineer · 2002–2005
- Operator
- Santos Ltd
- Scope
- Greenfield and brownfield operations projects across remote gas processing and field oil facilities, including the Moomba facility rebuild following a major industrial incident
† Santos Ltd — Operations Brownfield Projects is early-career operations and brownfield project work. It is shown here because it is where the operations-phase experience comes from, but it is not counted among the eight major projects.